Biomass Boiler Project & Main Conveyor

Georgia Pacific

Zachary, Louisiana
  • Bio Mass Boiler construction and rough set equipment with piping
  • Set steel drum over the boiler
  • 60 men average for 8 months
  • Installed equipment, including cone-configuration boiler with maxer configuration of two 300-ton cranes.​
  • 2 Crane path working from different directions. One equipped with superlift to make larger modules and set in big pieces.
  • Set equipment with maxer configuration (2) 300 ton cranes.