Biomass Boiler Project & Main Conveyor
Georgia Pacific
Zachary, Louisiana
- Bio Mass Boiler construction and rough set equipment with piping
- Set steel drum over the boiler
- 60 men average for 8 months
- Installed equipment, including cone-configuration boiler with maxer configuration of two 300-ton cranes.
- 2 Crane path working from different directions. One equipped with superlift to make larger modules and set in big pieces.
- Set equipment with maxer configuration (2) 300 ton cranes.