AK Steel

Rockport, Indiana
  • Fast Track Project (Completed in 9 Months, scheduled for 12)​
  • Erected 25,000 tons of steel (3 Buildings)​
  • Erected 30 Overhead Cranes​
  • Erected 238’ Tall Looping Tower​
  • Peak Manpower - 312​
  • Installed 1,500,000 SF of Siding​
  • Installed 1,750,000 SF of Standing Seam Roofing​
AK Steel